How to procure renewable energy in Asia in 2026 - Step by step guide

You have a renewable electricity target. Now you need a supplier shortlist, comparable prices and a contract you can defend to your CFO.

If you are a procurement manager in Asia, work through these five steps. Start with your electricity bills, then use the questions below in your next supplier discussion.

YOUR PROCUREMENT ROADMAP (click on each to navigate!)

Your five-step buying guide

Practical tips & checksvPPA financial considerations

STEP 1Build your buying brief

Before asking for quotes, put internally these essentials on one page:

  • Demand: what were your electricity bills for the past year, load profile and planned shutdowns.
  • Site: which location, the available roof or land, ownership or remaining lease.
  • Target: what renewable MWh required and delivery deadline and why.
  • Limits: upfront budget, acceptable contract length and existing electricity commitments.

Bring in Facilities, Finance, Legal and Sustainability now.
Get agreement on the brief before suppliers start pricing different assumptions.

PROCUREMENT TIPBefore requesting prices

Get internal approval on which sites, volumes, delivery date and contract limits.

STEP 2Choose your route: start with your site

Follow the questions below to build your shortlist. A route belongs in your tender only after local eligibility is confirmed.

2A

Usable roof or land, with daytime consumption?

6865dee79aadcd3148fc36ff_Samyang-Foods-Miryang-2nd-Plant-Completed-drone
On-site solar at Samyang Food Worldwide export Buldak Ramyeon plant, South Korea, built by Peak.

Yes: assess on-site solar and match output to operating hours, including shutdowns. Want to avoid upfront system investment? Compare on-site PPAs. Have capital and accept ownership responsibilities? Compare owned solar, including maintenance.
No, or insufficient output: move to B.

2B

Still have electricity demand to cover?

peak-energy-japan-industrial-rooftop-solarAssess a physical off-site PPA where permitted. Ask who delivers the electricity, which intermediaries are involved and what reaches your meter at the quoted price.

 

Buy only the volume not already covered by other commitments.

 

2C

Need coverage before a project can start?

Certificates alone: you buy environmental attributes separately; your electricity supply stays unchanged.
Utility renewable offer: assess an electricity supply product bundled with renewable attributes.
For either, check the premium, certificate eligibility and retirement evidence. For example, Singapore RECs became stricter in Octobertober 2026: only local RECs can be claimed.

FINANCIAL CONTRACT · vPPASeparate track: considering a virtual PPA?

A vPPA is a financial price-settlement contract with agreed environmental attributes; site electricity is purchased separately.
Check your regulatory framework. Then ask Finance and Treasury to approve the structure and Sustainability to check reporting eligibility.

Storage? Add it only for a defined operational or cost need. It stores electricity; it does not generate it.

STEP 3Send one brief to every bidder

Issue the same request for proposals (RFP), with a common response template. Ask each supplier to complete these fields:

  • Price and annual increases
  • Volume commitments
  • All extra charges
  • Start date
  • Contract term
  • Maintenance
  • Certificate ownership
  • Exclusions

Request evidence of committed financing, comparable operating projects, the delivery team profile and a schedule backed by permitting and connection milestones.

Copy into your RFP: “Please price the base specification separately from alternatives and identify every assumption, exclusion and buyer responsibility.”

PROCUREMENT TIPPause the tender if…

Do not shortlist on promises alone. Ask the bidder to substantiate funding, operating references and delivery milestones.

STEP 4Compare the bill, then test the downside

For physical supply, compare the same demand and period: PPA payments, remaining grid purchases, delivery fees, certificates not included and any works you must fund.

Bid A or Bid B?

Illustrative example, not actual supplier offers.

Bid A
Lower tariff, delivery fees excluded.

Bid B
Higher tariff, delivery fees included.

Your move: request the same delivered-cost basis before ranking either offer.

vPPA · CHECK THE FINANCIAL SETTLEMENT

For a virtual PPA, model settlement cash flows alongside your separate electricity bill.
Check our CFO guide to prepare your approval case.

Ask every shortlisted bidder: “What happens to our costs if demand falls, grid prices drop or your project starts late?”

STEP 5Run the pre-signature check

Ask Legal and Finance to turn the agreed assumptions into written obligations, remedies and exit terms:

  • Performance: what happens if output or delivery falls short?
  • Flexibility: what do you pay during shutdowns, relocation or early termination?
  • Certificates: who owns them, retires them and supplies the evidence?
  • Accountability: who tracks milestones, invoices and performance after signing?

Have Sustainability confirm certificate eligibility against the applicable Scope 2 criteria and customer requirements. Do not claim renewable electricity use if its attributes have been sold to someone else.

PROCUREMENT TIPDo not sign with certificate rights unresolved

Confirm the owner, reporting beneficiary, retirement process and evidence deadline in the contract.

Local checks before you commit 

Japan: ask how the retailer will arrange off-site supply through the grid* (METI).
South Korea: compare direct and KEPCO-mediated PPAs, including K-RE100 evidence* (Korea Energy Agency).

*Confirm current eligibility, charges and reporting rules for each project.

To Wrap up: Your five-point procurement checklist

  1. Agree the brief. Align your sites, demand, targets and contract limits internally.
  2. Confirm the route. Check local eligibility, physical delivery and environmental attributes.
  3. Tender on one basis. Give every bidder the same specification and response template.
  4. Compare total cost. Include extra charges and test lower demand, price changes and delays.
  5. Secure the contract. Resolve performance, flexibility, certificate rights and accountability before signing. 

Your next action: explore your options with us

Tell us where your sites are, when you need renewable electricity and what you want to achieve. We’ll help identify which options merit a closer assessment.

You do not need a complete procurement pack to start the discussion. Share what you know with us; detailed site data can follow.

 

Sources: Adapted from the EuroCham Singapore and Peak Energy 2025 'How to procure Renewable energy in Asia" corporate procurement white paper.